NEW QUESTION 15
Which of the following statements apply to project versions? Note: There are 2 correct Answers to this question.
- A. Project versions can be created automatically based on user status.
- B. Manually created project versions always require a project version profile.
- C. Project versions are mandatory for Milestone Trend Analysis (MTA).
- D. Project versions can be changed.
Answer: C,D
NEW QUESTION 16
What are the prerequisites for delivering materials from the project? Note: There are 2 correct Answers to this question.
- A. A delivery document type must be configured.
- B. A sold to party is necessary.
- C. A sales order must be created in advance.
- D. A shipping point is necessary.
Answer: B,D
NEW QUESTION 17
You have saved a network and activities with assigned material components. As soon as you release the network, you receive the error message "Business transaction cannot be carried out". What could be the reason for this error message?
- A. Missing material availability
- B. Missing authorizations to release material components
- C. Missing reservations for material components
- D. Missing budget for material components
Answer: B
NEW QUESTION 18
You want to use subnetworks during the project. Which of the following statements describes subnetworks?
- A. A subnetwork cannot be defined for a superior subnetwork.
- B. Subnetworks must be scheduled separately from the superior network.
- C. The scheduling type of a subnetwork is always copied from the superior network.
- D. Maintenance orders can be defined as subnetworks.
Answer: D
NEW QUESTION 19
To which object can you assign a factory calendar?
- A. Milestone
- B. Relationship
- C. Network header
- D. Material component
Answer: C
NEW QUESTION 20
Float time is calculated during scheduling. Which of the following statements about float time are correct? Note: There are 3 correct Answers to this question.
- A. The float time of WBS elements is calculated by extrapolation.
- B. By default, critical activities have a float time, which is less than or equal to zero.
- C. The maximum size of a free float is as large as the total float of an activity.
- D. Activities with the time constraint "Must start on" always have a negative float time.
- E. Float time can be negative.
Answer: B,D,E
NEW QUESTION 21
In your project, you work with a network and external activities. You have created a purchase requisition. The corresponding purchase order is created as well. Now, you increase the quantity of the external activity. How does the system support this scenario?
- A. The purchase order is updated automatically to match the new quantity while saving the project.
- B. The system automatically creates a new purchase requisition with the difference to the original quantity.
- C. A workflow can be triggered to inform the purchasing group.
- D. The purchase order can be updated in Goods Receipt for Purchase Order (MIGO).
Answer: C
NEW QUESTION 22
Budgeting is implemented for projects. The budget has been adjusted several times. What standard report type provides an overview of adjustments on the budget?
- A. Structure overview for budgets
- B. Cost element report on budget updates
- C. Line item report for budgets
- D. Hierarchical report on budget updates
Answer: C
NEW QUESTION 23
You have activated the workflow for confirmation variances in SAP Project System. Who is the receiver of this workflow item?
- A. The person responsible for the work center
- B. The person responsible for the superior WBS element
- C. The MRP controller for the network
- D. The person responsible for the network activity
Answer: C
NEW QUESTION 24
What are some of the possible functions in user status profiles? Note: There are 2 correct Answers to this question.
- A. Ensure user status must always be set manually.
- B. Restrict setting user status for individual users.
- C. Allow business processes forbidden by SAP system status.
- D. Utilize priorities for setting the user status.
Answer: B,D
NEW QUESTION 25
A customer needs to analyse the capacity requirements of their network activities. Which reports do you recommend? Note: There are 2 correct Answers to this question.
- A. Hierarchical reports
- B. Resource reports
- C. Structure information system reports
- D. Cost element reports
Answer: C
NEW QUESTION 26
You want to make sure that certain tasks must start on a given date. Where can you maintain constraints for start dates?
- A. Activity
- B. Milestone
- C. Activity element
- D. Network header
Answer: A
NEW QUESTION 27
Which sales documents can update planned revenues on WBS elements? Note: There are 2 correct Answers to this question.
- A. Sales order
- B. Quotation
- C. Inquiry
- D. Billing
Answer: A,B
NEW QUESTION 28
Which sets of dates can be used to schedule networks? Note: There are 2 correct Answers to this question.
- A. Planned dates
- B. Forecast dates
- C. Baseline dates
- D. Basic dates
Answer: B,D
NEW QUESTION 29
Which statements describe planned and actual revenue for WBS elements? Note: There are 2 correct Answers to this question.
- A. Planned revenue can be transferred from a sales quotation.
- B. Actual revenue is posted via a billing plan assigned to a WBS element.
- C. Planned revenue requires a sales order assigned to a WBS element.
- D. Actual revenue is posted via a billing document created from a sales order
Answer: A,D
NEW QUESTION 30
Which statement is valid regarding networks? Note: There are 2 correct Answers to this question.
- A. Relationships can be used to connect activities of different networks.
- B. Material components can be assigned to activity elements.
- C. A network can be activity-account-assigned and header-account-assigned.
- D. A network activity can be assigned to several WBS elements.
Answer: A,C
NEW QUESTION 31
How are earliest dates and latest dates of activities scheduled?
- A. Earliest dates are scheduled by backward scheduling, and latest dates by forward scheduling.
- B. Earliest dates and latest dates are scheduled by forward scheduling.
- C. Earliest dates are scheduled by backward scheduling, and latest dates by copying the earliest dates.
- D. Earliest dates are scheduled by forward scheduling, and latest dates by backward scheduling.
Answer: D
NEW QUESTION 32
You plan an activity that starts on February 1 and finishes on February 28. For this activity, you want to define a milestone for February 10 which should NOT be changed through scheduling. What do you recommend for milestone definition?
- A. Enter February 10 as fixed date.
- B. Enter an offset of 10 days to the start date of the activity.
- C. Enter 10 days as duration.
- D. Enter an offset of -18 days to the finish date of the activity.
Answer: A
NEW QUESTION 33
What could be a reason to use expert mode in the valuation method for results analysis?
- A. Assignments of different accounts for postings to financial accounting
- B. Usage of different line IDs
- C. Billing WBS elements belonging to different company codes
- D. Valuation in different currencies
Answer: A
NEW QUESTION 34
Which object is relevant in assembly processing to create an assembly order for the SD document?
- A. Item category
- B. Control key
- C. Requirement class
- D. Project profile
Answer: C
NEW QUESTION 35
An external component is assigned to a network activity. The delivery date for the purchase requisition depends on the dates of the network activity. What controls whether the delivery date is defined by the earliest or latest scheduled dates?
- A. The table of MRP controllers
- B. The network profile
- C. The scheduling parameters for the network
- D. The control key
Answer: C
NEW QUESTION 36
Which of the following is visible in the project planning board? Note: There are 2 correct Answers to this question.
- A. Maintenance orders assigned to an activity
- B. Project-relevant purchase orders
- C. Production orders assigned to WBS elements
- D. Capacity requirements
Answer: A,D
NEW QUESTION 37
You want to set up the field selection of the Cross-Application Time Sheet (CATS) in Customizing. Which influencing field do you use?
- A. Network profile
- B. Data entry profile
- C. Network type
- D. Project profile
Answer: B
NEW QUESTION 38
A customer project must be finished at a given due date. The project consists of WBS elements and networks. What scheduling type do you use?
- A. Forward
- B. Only capacity requirements
- C. Backward
- D. Current date
Answer: C
NEW QUESTION 39
You have created an internally-processed network activity, and assigned a work center and the work.
After saving, you discover that no planned costs are displayed in the cost element report for the activity.
What could be the reason? Note: There are 3 correct Answers to this question.
- A. The Determine Costs indicator in the network header rules out planned cost calculation.
- B. The formula for costing in the work center is incorrect.
- C. Integrated planning for the network is active.
- D. The duration is missing in the activity.
- E. The activity output price for the activity type and cost center assigned to the work center is not maintained.
Answer: A,D,E
NEW QUESTION 40
......