The "SAP Certified Application Associate - SAP S/4HANA Production Planning and Manufacturing" certification exam validates that the candidate possesses the fundamental and core knowledge required of the SAP S/4HANA Manufacturing consultant profile. This certification proves that the candidate has an overall understanding and in‐depth technical skills to participate as a member of a project team in a mentored role.

 

NEW QUESTION 33
You need to model goods receipt processing time in Detailed Scheduling. Which modelling options do you have? Note: There are 2 correct answers to this question.

  • A. Model a separate resource in the production data structure.
  • B. Model a transportation resource in the location master.
  • C. Model a handling resource in the location master and goods receipt time in the mater all master.
  • D. Model a resource inbound in the location master.

Answer: B,C

 

NEW QUESTION 34
What does forecasting in the demand planning cycle include? Note: There are 3 correct answers to this question.

  • A. Past quotation quantities
  • B. Past procurement quantities
  • C. One-off events
  • D. Past sales order quantities
  • E. Market intelligence

Answer: C,D,E

 

NEW QUESTION 35
The production plan is being disrupted by last minute demands that are entered in the system. Which is the most efficient way to handle last minute demands and protect the current production plan?
There are 2 correct answers to this question.
Response:

  • A. In the material master record, set MRP type to P1 and a planning time fence on the replenishment lead time of the material
  • B. Manually firm all planned orders for materials within the replenishment lead time of the material
  • C. In the stock requirements list, set a manual firming fence for a date based on the replenishment lead time of the material
  • D. In the material master record, set MRP type to P4 and a planning time fence on the replenishment lead time of the material

Answer: A,C

 

NEW QUESTION 36
Which options do you have to plan both quant ties and capacities during line loading in repetitive manufacturing? Note: There are 2 correct answers to this question.

  • A. Assign planned orders manual lying the planning table.
  • B. Run MRP with automatic selection of production version.
  • C. Run PP/DS heuristics for repetitive manufacturing.
  • D. Run MRP with quota arrangement.

Answer: C,D

 

NEW QUESTION 37
Before a user can add multiple production versions in a material master, what information should be collected?
There are 3 correct answers to this question.
Response:

  • A. Work center hierarchy
  • B. Lot sizes
  • C. BOM status
  • D. Validity dates
  • E. Task list group number

Answer: B,C,D

 

NEW QUESTION 38
A planner updated a production order status from partially confirmed "PCNF" to technically completed "TECO" by mistake.
What impact would this have to other users for this specific production order?
Please choose the correct answer.
Response:

  • A. The warehouse clerk still carry out goods issue transactions
  • B. The production manager can still see the capacity requirements
  • C. The production operator cannot enter additional confirmations
  • D. The buyer can still see component reservations

Answer: C

 

NEW QUESTION 39
You want to triggering-house production of a semi-finished mater al before a sales order for the corresponding finished good is received. Which planning strategy supports the consumption of planned independent requirements for the semi-finished material?

  • A. Make-to-order production (20)
  • B. Planning without final assembly (50)
  • C. Planning with final assembly (40)
  • D. Planning at assembly level (70)

Answer: B

 

NEW QUESTION 40
Which bill of material (BOM) categories can you define in SAP S/4HANA? Note: There are 2 correct answers to this question.

  • A. Functional Location BOM
  • B. Work Center BOM
  • C. Sales Order BOM
  • D. Class BOM

Answer: A,C

 

NEW QUESTION 41
In your plant, MRP is activated. Which options do you have to exclude a material from the MRP run? Note:
There are 2 correct answers to this question.

  • A. Use a specific material group
  • B. Use a specific MRP type.
  • C. Use a specific material status.
  • D. Use a specific MRP controller.

Answer: B,D

 

NEW QUESTION 42
What are attributes of the SAP S/4HANA Simplification list?
There are 3 correct answers to this question.
Response:

  • A. It is only a grouping of related technical simplifications
  • B. It was created for better planning and estimation of your way to S/4HANA
  • C. It can have a business and a technical impact
  • D. It details transaction and solution capabilities at a functional level
  • E. It contains references to the relevant training material

Answer: B,C,D

 

NEW QUESTION 43
What does the bill of material usage (BOM usage) control at the BOM item level?
Response:

  • A. Default unit of measure
  • B. Default values for the item status
  • C. Allowed material type
  • D. Maximum allowed low-level code

Answer: C

 

NEW QUESTION 44
What is the purpose of a reporting point confirmation in repetitive manufacturing? Note: There are 2 correct answers to this question.

  • A. To determine the work in progress along the production line
  • B. To reduce the total production lead time for along production line
  • C. To stage different components for a production line simultaneously
  • D. To provide timely updates of inventory management for the staged components

Answer: A,D

 

NEW QUESTION 45
You want to schedule an operation finitely, without moving other operations. Which scheduling strategy do you select?

  • A. Find Slot
  • B. Scheduling working time only
  • C. Squeezing
  • D. Insert operation

Answer: A

 

NEW QUESTION 46
The settings for MRP can be maintained at different levels. If settings have been maintained in different places, in which sequence does the system search for the MRP settings?
Please choose the correct answer.
Response:

  • A. Material Master -> MRP Group -> Plant Settings
  • B. Plant Settings -> MRP Group -> Material Master
  • C. Material Master -> Plant Settings -> MRP Group
  • D. MRP Group -> Material Master -> Plant Settings

Answer: A

 

NEW QUESTION 47
Where can you maintain consumption mode and consumption periods for planning strategies?
There are 2 correct answers to this question.
Response:

  • A. In the requirements class
  • B. In the plant parameters
  • C. In the material master
  • D. In the MRP group

Answer: C,D

 

NEW QUESTION 48
How can you carry out cost object controlling for production orders? Note: There are 2 correct answers to this question.

  • A. Product-related
  • B. Milestone-related
  • C. Order-related
  • D. Cost-related

Answer: A,C

 

NEW QUESTION 49
Which reports can you access via the order and resource reporting transaction in advanced planning?
There are 3 correct answers to this question.
Response:

  • A. Operation list
  • B. Production overview
  • C. Production list
  • D. Planning file entries
  • E. WIP list

Answer: A,B,E

 

NEW QUESTION 50
You are using the document management system (DMS) . Where should the DMS document links be assigned, to have them automatically copied to production orders?
There are 2 correct answers to this question.
Response:

  • A. Work center
  • B. Bill of material
  • C. Material master
  • D. Routing header

Answer: B,C

 

NEW QUESTION 51
Which of the following data objects are updated when a user confirms an operation?
Please choose the correct answer.
Response:

  • A. Production order header status
  • B. Warehouse transfer order status
  • C. Production order total order quantity
  • D. Shop floor information system

Answer: D

 

NEW QUESTION 52
Which of the following objects can you release so that the business transactions for process order execution and process management can be executed?
There are 2 correct answers to this question.
Response:

  • A. Individual phases
  • B. Individual control recipes
  • C. Individual process instructions
  • D. Individual operations

Answer: A,D

 

NEW QUESTION 53
What are some of the SAP Fiori user types?
There are 3 correct answers to this question.
Response:

  • A. Developer
  • B. Employee
  • C. Occasional
  • D. Expert
  • E. Business partner

Answer: A,C,D

 

NEW QUESTION 54
In a production process, you need a certain amount of liquid as input material. The source tank is directly connected to the reactor. How can you process consumption postings?

  • A. Kanban
  • B. Picking list
  • C. Transfer Order
  • D. Backflushing

Answer: B

 

NEW QUESTION 55
You are using heuristic SAP_ERP_001. Which of the following criteria are included in the automatic source determination logic when a planned order is created?
Please choose the correct answer.
Response:

  • A. Quota arrangement
  • B. Delivery date
  • C. Costs
  • D. Component availability
  • E. Vendor rating

Answer: A

 

NEW QUESTION 56
Which of the following is an advantage of MRP Live and NOT available in classical MRP?
Response:

  • A. MRP Live can propose alternative solutions
  • B. MRP Live can create production orders automatically
  • C. MRP Live can priorities demand from sales orders
  • D. MRP Live can plan materials with recursive BOMs

Answer: A

 