NEW QUESTION # 13
A customer has an Aruba wireless network. which includes two MC 7205s and an MM at the network core. The company now wants to accommodate 50 mobile trainers These trainers travel around the world and run training events. The trainers often need to access materials in the company data center, but cannot reach materials when they are on the road.
The company wants to give the mobile workforce a secure way to reach the materials they need no matter where they are.
including in public spaces like the hotels where they often leach. The customer also requires that the solution be as cost effective as possible while meeting the requirements.
Which plan meets the needs of the mobile Trainers?

  • A. Add 50 VIA licenses to the MM, and deploy two 7005 MCs in the DMZ.
  • B. Add 50 RAPs: add 50 Enterprise licenses to the MM, and add two 7005 MCs in the DMZ.
  • C. Add 50 RAPs; add 50 Enterprise licenses and 50 VIA licenses to the MM
  • D. Add so PEFV licenses to the MM. and add an additional 7205 MC to the core.

Answer: C


NEW QUESTION # 14
A company already has an Aruba wireless network The network currently consists of:
* oneMM-HW-1k
* two 7210 MCs in the network core
* two 721GMCsintheDMZ
* 200 AP-515S in Building 1 and Building 5
100 AP-515S each In Building 2r Building 3, and Building 4
The customer now wants to assess if it needs local Mobility controllers (MC) for any buildings:
- Building 1 is the main office building for the campus. It supports the highest number of APs. It connects to the network core without an aggregation layer.
* Building 2 is further away from the Building i. and no roaming is provided between it and the other buildings its access layer connects to the network cone with a pair of Aruba CX 6300M aggregation switches.
* Building 3 is further away from the other buildings, it connects to the network core without an aggregation layer.
The Guest SSID traffic should be tunnelled to the DMZ controllers
' Building 4 has its own local datacenter and Internet connection. The company would like it to be able to operate completely autonomously if its aggregation layer loses connectivity with the core.
* Building 5 is further away from the other buildings, it connects to the network core without an aggregation layer.
This building has been assigned to a partner that would like to manage a dedicated SS1D using the shared AP infrastructure.
In which two buildings should the network architect plan local mobility controllers (MCs)? (Select two)

  • A. Building 5
  • B. Building 4
  • C. Building 1
  • D. Building 2
  • E. Building 3

Answer: C,E


NEW QUESTION # 15
Which scenario Indicates the need for a wireless mesh?

  • A. A hospital needs to provide high availability for wireless services in certain areas which support very critical wireless medical devices. Devices must always be in range of at least two APs.
  • B. A nsstorical building has some wired areas and a few areas with no wired or wireless connectivity, walls and ceilings have asbestos. The company needs wireless access across the site.
  • C. A company has a small branch office with just one RAP. The company has noticed that performance is poor in some areas of the network and wants to add another AP.
  • D. A company needs to provide seamless roaming and wireless access between two buildings. The buildings are about 60 feet (18 m) apart.

Answer: D


NEW QUESTION # 16
A company has several remote sues that operate more or less autonomously. Each site has ns own local services and Internet connection However the company does have a main office with a few centralized resources that the company would like to make available to remote office employees over the Internet connection. Sites range in size and require between 10 and 20 APs.
The customer requires the most cost-effective solution that meets the requirements.
Which solution should the architect recommend for each remote site?

  • A. Remote APs (RAPs) with IPsec tunnels to a main office MC
  • B. Campus APs (CAPS) with CPSec control channels to a main office MC
  • C. Campus APs (CAPs) with a local MC that has an SD-WAN license
  • D. an IAP cluster with an IPsec tunnel to a main office MC

Answer: C


NEW QUESTION # 17
Refer to the exhibit.

A customer needs a wired upgrade for a building on its main campus. The exhibit shows the switches that the architect has selected for each closet and me existing cabling. The customer is not open to changing the cabling.
The customer requires link redundancy for the uplinks from each closet and for the links from the building to the core. In non link failure situations, the uplinks from each closet must support at least 20Gbps, and the building as a whole must have at least 20 Gbps to the core in non link failure situations Which two options Tor connecting the closets to the network core are valid? (select two.)

  • A. Combine the nine switches on the three floors into a single switch stack with the MM QM3 fiber cables in a ring topology. Connect two Floor 1 members to the network core with one fiber connection each.
  • B. Connect the switch stack on each floor directly to the network cone on two "fiber connections per floor. Achieve this by patching the inter-floor fiber through to the inter-building fiber.
  • C. Add two aggregation switches in the Floor 1closet. Connect the switch stack for each closet to the aggregation switches on two fiber links each and the aggregation switches to the core on two fiber links.
  • D. Connect me Floor 2 switch stack to Floor 1 with two fiber connections, DO me same for Floor 3. connect the Floor 1 switch stack to the network cone with two fiber connections.
  • E. Combine the nine switches on all three floors into a single switch slack with stacking cables in a ring topology.
    Connect two Floor f members to the network core with one fiber connection each

Answer: B,C


NEW QUESTION # 18
Refer to the exhibit.
A customer has an existing network with ArubaOS switches, Aruba 7205 controller, and 802.11ac APs. The customer needs a wired upgrade for their campus network and wireless upgrade with 802,11ax APs and would like to get all the functions of AP.
The customer has one building with 3 floors with the following wired devices,
* 200 VOIP phones
* 8 printers
* security cameras
The architect plans to propose 75 AP-535s.
The security cameras are a high definition pan-tilt-zoom with heaters for harsh environments that require more than 45 W to function, Which exhibit shows an access switch mat meets the customer needs?
A)

B)

C)

D)

  • A. Option D
  • B. Option C
  • C. Option A
  • D. Option B

Answer: A


NEW QUESTION # 19
Refer to the exhibit.

Exhibit: A49.01114316-102
The architect has determined that this building requires two 10GPE links to the data center.
What is the correct transceiver type for the links?

  • A. SFP+ SR
  • B. SFP+ LR
  • C. SFP+ LRM
  • D. 3FP+ LRM with mode conditioning

Answer: C


NEW QUESTION # 20
Refer to the exhibit.

A company needs a new wireless solution for its multi-site network. All branch sites must connect to the main site through secure tunnels over the Internet. The customer requires full redundancy for the Mobility Controllers (MC). Including stateful faiEoverand seamless roaming for the main site.
The architect plans to propose:
- 500 RAPS
- 100 APs at the main campus
- two 7205 MCs
- two 7210 MCS
- one MM appliance
The exhibit snows the existing wired network at the main site, which has a single building with two large floors.
Following the best-practices on design, performance and security, where should the architect plan to connect the MCs?
{Potential locations are numbered in the exhibit.)

  • A. two 7205 MCS at 1; two 7210 MCS at 2
  • B. all of the MCs at 2
  • C. two 7205 MCs at 2; two 7210 MCs at 1
  • D. one 7205 MC at 3 and one at 4; two 7210 MCs at 1

Answer: B


NEW QUESTION # 21
A customer has multiple medium and large branch sites, eacri of which requires between S ana 16 APs and supports between 200 and 600 wireless clients, Every branch site has an Internet connection, which it uses to reach the central data center. The customer would prefer the WAN links to be optimized in the solution.
Different use cases require SSID's for tunneled traffic from remote sites to central location, traffic that must remain local on the remote site, and traffic which would need to egress out from remote site Internet connection.
Which branch office solution best meets the customer needs?

  • A. CAPS and branch office controllers
  • B. IAPs with branch office controllers
  • C. RAPs and branch office controllers
  • D. lAPs with Aruba central

Answer: D


NEW QUESTION # 22
A customer has an existing; Aruba wireless solution to provide wireless access for employees. The solution Includes Aps, mobility controllers (MCs) at the network core, and a Mobility Master (MM} A customer would like to set up a separatelymanaged guest network and have the traffic go directly to the DMZ.
What should the architect suggest as the simplest solution that meets the requirements?

  • A. Use MulitZone, and put a mobility controller in Itie DMZ.
  • B. Double the number of APs and controllers.
  • C. Add APs in a dedicated AP group to support only the guest network SSID.
  • D. Have a dedicated mobility controller in the DMZ managed by the same MM

Answer: A


NEW QUESTION # 23
Refer to the exhibit.

A customer requires a core switching solution for a very large multi-building campus with about 30;ooo wireless clients and devices. The network will have a flat topology as shown in the exhibit, and MCs will forward all wireless traffic to the core for routing.
The customer had considered Aruba 5400R Series switches, but the architect recommends Aruba S320 switches Instead.
How should the architect justify this recommendation?

  • A. The 8320 switches are required to eliminate the aggregation layer as the customer desires.
  • B. The 8320 switches have greater performance and larger ARP tables than the 54Q0R Series, as is necessary for a network this size.
  • C. The 3320 switches offer more extensive mobility integration features with Aruba MCs and APs than the 54C0R Series switches do.
  • D. The 3320 switches support a higher density of 10GbE fiber ports than the 5400R Series.

Answer: C


NEW QUESTION # 24
Refer to the exhibit.

The network architect has created the 60M shown in the exhibit tor a complete new wired ana wireless solution for a customer. This solution the customer wants to discover and manage every component or the network in Airwave, including twins, MCS, APS, and switches.
How many AirWave licenses dees the architect need to add?

  • A. 0
  • B. 1
  • C. 2
  • D. 3

Answer: B


NEW QUESTION # 25
The architect plans to recommend an upgrade to Aruba CX switches
What is one requirement for the new solution that justifies this recommendation?

  • A. the requirement to support secure IPsec tunneling at the aggregation layer
  • B. the requirement to support larger ARP tables at the aggregation layer
  • C. the requirement to support smart Rate at the access layer
  • D. the requirement to support tunneled-node at the access layer

Answer: A


NEW QUESTION # 26
Compare the scenarios below. For which scenario do AP-575S meet the needs?

  • A. The customer needs APs for an indoor stadium that requires overhead coverage and directional antennas.
  • B. The customer needs APs for an Indoor nigh density environment In which tne customer prefers dual 5GHz operation.
  • C. The customer needs APS mounted to a concrete building exterior to provide coverage in a 90 foot (27m) radius from the building.
  • D. The customer needs to mount APs in an outdoor area, but that area only has fiber cable available,

Answer: D


NEW QUESTION # 27
A nospltai needs an upgrade to 802.11ax for its wireless network, which needs to provide complete coverage The hospital has a concrete exterior and uses drywalls lor all of the interior walls with a few exceptions as mandated for safety The building has 10fool (3 m) ceilings.
The hospital prefers to avoid the deployment of APs in rooms if possible. Exceptions include reception areas and lounges.
The wireless network must support wireless medical devices, voice communicators for medical star, laptops in nurse stations, medical staff tablets, and visitor and patient personal devices. All of these devices support both the 2.4GHz and 5GHz band.
The exhibits below show one wing of one floor of the hospital. This wing is about 2S.Q0D square feet {2GQQ sq, m). The unlabeled rooms along the bottom of the wing are patient rooms' other rooms such as lounges and the MR] room are labeled. This area has:
* up to SO concurrent patients and visitors, who might have up to two devices
* 40 concurrent staff members, who might have up to three devices
* about 200 medical and other types of wireless devices
The architect has already planned to place APs in stairwells on another floor.
Which AP plan for this wing of this floor meets the customer needs?
A)

B)

C)

D)

  • A. Option C
  • B. Option A
  • C. Option B
  • D. Option D

Answer: B


NEW QUESTION # 28
What is one reason to deploy an Aruba CX switch when compared to an ArubaOS switch?

  • A. to obtain higher wattage power modules for enhanced PoE+ support
  • B. to support Zero Touch provisioning (ZTP)
  • C. to obtain API-enabled programmability for greater automation
  • D. to support Aruba Dynamic Segmentation

Answer: A


NEW QUESTION # 29
What is one piece of additional information architects should obtain from the customer before they design the wireless solution?

  • A. the average number of users per loT device
  • B. the distance between the locations where cameras will be installed and the wiring closet on each floor
  • C. the power requirements for the wireless loT devices and security cameras
  • D. the authentication and encryption capabilities for loT devices and security cameras

Answer: B


NEW QUESTION # 30
Refer to the exhibit.


A customer needs to support resilient wireless services
What is one way that this design helps to minimize me impact of a railed access layer switch on these services?

  • A. The switches support Smart Rate and dual home AP connections.
  • B. The 8400s and G405s use Virtual Switching Extension (VSX) in cone and access.
  • C. Each access layer switch has two redundant links to the core.
  • D. APS in the same area connect to different switches.

Answer: A


NEW QUESTION # 31
......


Obtaining the Aruba Certified Design Expert certification requires passing both the written and practical exams. The practical exam, which is taken after passing the written exam, requires candidates to design and present a network solution using Aruba products and solutions. The ACDX certification is a highly respected certification in the industry and is recognized by many organizations worldwide.

 