PMI PMI-SP Exam Overview:
| Certification Vendor: | PMI (Project Management Institute) |
|---|---|
| Exam Name: | PMI Scheduling Professional (PMI-SP) Certification Exam |
| Exam Number: | PMI-SP |
| Passing Score: | Not published; pass/fail based on psychometric analysis |
| Certificate Validity Period: | 3 years (requires 30 PDUs for renewal) |
| Available Languages: | English |
| Exam Price: | Member: USD $520 | Non-Member: USD $670 |
| Exam Format: | Multiple-choice questions, Computer-based testing (CBT), Online proctored / Test center |
| Related Certifications: | PMP PMI-RMP PMI-PBA |
| Real Exam Qty: | 170 (150 scored, 20 unscored pretest) |
| Exam Duration: | 210 minutes |
| Recommended Training: | PMI-SP Exam Content Outline PMI-SP Certification Handbook |
| Exam Registration: | Pearson VUE Scheduling PMI Official PMI-SP Registration |
| Sample Questions: | ![]() |
| Exam Way: | Computer-Based Testing (CBT) at Pearson VUE centers or online proctored |
| Pre Condition: | Option 1: Secondary degree + 40 months scheduling experience (last 5 years) + 40 hours scheduling education; Option 2: 4-year degree + 24 months scheduling experience (last 5 years) + 30 hours scheduling education; Option 3: GAC-accredited degree + 12 months scheduling experience (last 5 years) + 30 hours scheduling education |
| Official Syllabus URL: | https://www.pmi.org/certifications/scheduling-sp |
PMI PMI-SP Exam Syllabus Topics:
| Section | Weight | Objectives |
|---|---|---|
| Topic 1: Schedule Monitoring and Controlling | 35% | - Analyze variances, EVM, and critical path - Track schedule progress and performance - Apply compression and optimization techniques - Forecast schedule outcomes - Manage schedule changes and control |
| Topic 2: Schedule Strategy | 14% | - Identify constraints, assumptions, and standards - Select scheduling tools and techniques - Establish schedule management plan and policies - Define scheduling methodology and approach |
| Topic 3: Schedule Planning and Development | 31% | - Apply CPM, PERT, and network analysis - Sequence activities and define logical relationships - Estimate durations and resource requirements - Develop baseline schedule and calendars - Create work breakdown structure and activity definitions |
| Topic 4: Schedule Closeout | 6% | - Finalize schedule records and performance review - Archive schedule data and artifacts - Document lessons learned |
| Topic 5: Stakeholder Communications Management | 14% | - Manage stakeholder expectations - Distribute schedule information - Develop communication strategy for schedule - Report schedule status and impacts |
PMI-SP Questions and Answers
The package includes 326 practice questions for the PMI-SP exam, all verified and arranged in a well-balanced mix of difficulty to support progressive study.
- Schedule Monitoring and Controlling (35%)
- Schedule Strategy (14%)
- Stakeholder Communications Management (14%)
Let the topic weights guide how you split your study hours.
The PMI Scheduling Professional questions are spread across a well-proportioned range of difficulty, from fundamentals to challenging items. That distribution lets you build confidence session by session, and by the time the real test approaches, you have already faced everything it can reasonably throw at you.
Option 1: Secondary degree + 40 months scheduling experience (last 5 years) + 40 hours scheduling education; Option 2: 4-year degree + 24 months scheduling experience (last 5 years) + 30 hours scheduling education; Option 3: GAC-accredited degree + 12 months scheduling experience (last 5 years) + 30 hours scheduling education
The PMI-SP exam contains 170 (150 scored, 20 unscored pretest) questions within 210 minutes minutes. Rehearsing under the same limit on the CertkingdomPDF simulator builds calm, practiced pacing.
PMI-SP Exam Content Outline: Visit official page
PMI-SP Certification Handbook: Visit official page
PMI Official PMI-SP Registration: register for PMI-SP
Pearson VUE Scheduling: register for PMI-SP
To pass PMI-SP you need Not published; pass/fail based on psychometric analysis, and the official exam fee is Member: USD $520 | Non-Member: USD $670. Fixing both numbers early keeps your practice target concrete.
Our service comes down to three commitments. First, the staff works around the clock online so customer demands about PMI Scheduling Professional are met the moment they arise. Second, the team is strictly discreet: customer personal information has never been leaked, and your privacy remains protected. Third, our experts watch the renewal of the question bank, and once a change is found, the updated material goes straight to your mailbox.
PMI Scheduling Professional Sample Questions:
You are the project manager of a project that has a budget of $675,000 and you have completed 40 percent of the project work. Your project is supposed to be 60 percent complete but you are actually only 40 percent complete. Due to some errors, however, you have actually spent $335,000 of the budget. Management wants to know what the project's cost performance index (CPI) is. What value do you report?
- A. -$135,000
- B. .81
- C. .67
- D. -$65,000
Correct Answer: B 🗳️
Explanation: Only visible for CertkingdomPDF members. You can sign-up / login (it's free).
You work as a project manager for BlueWell Inc. Management has asked you not to communicate performance unless the CPI is less than 0.96 or the SPI dips below 0.98. What type of report would you create for management, if these instances develop in your project?
- A. Performance management report
- B. Cost variance report
- C. Schedule variance report
- D. Exceptions report
Correct Answer: D 🗳️
Explanation: Only visible for CertkingdomPDF members. You can sign-up / login (it's free).
You are the project manager of the HQQ Project. Your project is running late by ten percent of where you should be at this time. Management is concerned and they'd like to know what your schedule variance is. Considering that the project has a BAC of $567,899, you are thirty percent complete, and you have spent $179,450. What is the schedule variance for this project?
- A. -$56,790
- B. -$30,268
- C. -$45,789
- D. There is not enough information to know.
Correct Answer: A 🗳️
Explanation: Only visible for CertkingdomPDF members. You can sign-up / login (it's free).
You work as a project manager for BlueWell Inc. You are calculating the performance indexes of your project. The cost variance (CV) of your project is 30. What does this figure depict?
- A. Costs are higher than planned.
- B. Costs are lower than planned.
- C. Project is behind the schedule.
- D. Costs are right on target.
Correct Answer: B 🗳️
Explanation: Only visible for CertkingdomPDF members. You can sign-up / login (it's free).
Thomas works as a contract-based project manager for BlueWell Inc. Management has hired Thomas to manage a high-risk project because Thomas has years of experience with this technology and similar project. Thomas would like to use his own templates for the project schedule, quality, and risk management approach. Management is fine with this, except after reviewing the template they had preferred Thomas to use 24-hour time periods for his project calendar rather than the 8-hour time periods as indicated. Thomas agrees, but now he has to update what document in his project management plan?
- A. Schedule management plan
- B. Activity attributes
- C. Resource calendar
- D. Project calendar
Correct Answer: D 🗳️
Explanation: Only visible for CertkingdomPDF members. You can sign-up / login (it's free).
Viewing page 1 out of 66 pages.
Viewing questions 1-5 out of 326 questions.