CompTIA PK0-004 Exam Overview:
| Certification Vendor: | CompTIA |
|---|---|
| Exam Name: | CompTIA Project+ Certification Exam |
| Exam Number: | PK0-004 |
| Exam Format: | Multiple Response, Multiple Choice |
| Exam Duration: | 90 minutes |
| Real Exam Qty: | Maximum of 95 |
| Passing Score: | 710 (on a scale of 100–900) |
| Exam Price: | USD ≈ 358 (may vary by region and test center) |
| Related Certifications: | CompTIA Project+ (PK0-005) |
| Available Languages: | English |
| Certificate Validity Period: | No fixed validity; CompTIA recommends staying current with exam updates and may require continuing education to maintain certification relevance |
| Sample Questions: | ![]() |
| Exam Way: | Delivered through Pearson VUE test centers and CompTIA's authorized testing channels. |
| Pre Condition: | No formal prerequisite exam required; recommended 12 months of project management experience or equivalent practical application. |
| Official Syllabus URL: | https://www.comptia.org/en/certifications/project |
CompTIA PK0-004 Exam Syllabus Topics:
| Section | Weight | Objectives |
|---|---|---|
| Project Tools & Documentation | 21% | - Tools and Documentation Skills
|
| Project Basics | 36% | - Scheduling and Team Structures
|
| Project Constraints | 17% | - Managing Constraints and Risk
|
| Communication & Change Management | 26% | - Communication Methods and Change Control
|
Everything About Our CompTIA Project+ Certification Practice Questions
The CompTIA Project+ Certification exam requires a score of 710 (on a scale of 100–900) to pass, and the official registration fee is USD ≈ 358 (may vary by region and test center). Planning around both numbers helps you set a realistic budget and study schedule.
We believe useful study material should be accessible to every candidate, whatever their budget. That is why our prices are kept reasonable, why a free demo is open to everyone, and why discounts run from time to time — quality preparation should never be a privilege reserved for the few.
This package includes 797 practice questions for the CompTIA Project+ Certification exam. Every answer is verified by an experienced team of experts, so you can trust what you study.
You can contact our customer service online or describe your problem by email, and you will receive a reply with a solution as quickly as possible. Whether your question is about purchasing, downloading, or using the material, our staff treats your time as a priority and works the issue through with you until it is resolved.
The CompTIA Project+ Certification exam contains Maximum of 95 questions, and you will have 90 minutes minutes to complete them. Practicing under the same time pressure makes the real exam feel like a rehearsal.
No formal prerequisite exam required; recommended 12 months of project management experience or equivalent practical application.
You can confirm the current eligibility requirements on the official PK0-004 exam page before you register.
The CompTIA Project+ Certification practice questions are organized around the official exam objectives. Key topics include:
- Communication & Change Management (26%)
- Project Basics (36%)
- Project Constraints (17%)
Targeted practice against these topics is far more efficient than unfocused reading.
CompTIA Project+ Certification Sample Questions:
A project team has determined it will need to source data from a system that was not part of the project scope.
The role of the project manager is to analyze which of the following impacts?
- A. New software and hardware requirements
- B. Schedule, budget, and quality
- C. Technical design, schedule, and budget
- D. Business process impacts and resourcing
Correct Answer: A 🗳️
A project manager wishes to track a project's performance against the original approved schedule. Which of the following steps is necessary to capture the needed information?
- A. Set a baseline.
- B. Determine the milestones.
- C. Set phase gates
- D. Determine the critical path.
Correct Answer: A 🗳️
Based on the table below:
Which of the following is the critical path?
- A. B, C, D, E, H, I, L, M
- B. A, C, D, E, H, I, L, M
- C. B, C, F, G, J, K, L, M
- D. A, C, F, G, J, K, L, M
Correct Answer: A 🗳️
A project has fallen behind schedule. Upon investigation, the project manager determines that team members have implemented requirements relayed via impromptu hallway meetings with the client.
Which of the following should the project manager do to resolve this issue?
- A. Modify the project baselines.
- B. Implement change control management.
- C. Inform the stakeholders of the issue.
- D. Update the scope management plan.
Correct Answer: C 🗳️
Which of the following events would MOST likely trigger communications to the largest audience for a given organization?
- A. Completion of a task
- B. Business continuity response
- C. Quality audit
- D. Replacement of a subcontractor
Correct Answer: B 🗳️