No complicated setup, no extra software, no shipping. Pay for the CIMA Management Accounting material at CertkingdomPDF, click the link in the email that arrives within a minute, and your CIMAPRO19-P01-1 download finishes in about a minute more.
CIMA CIMAPRO19-P01-1 Exam Overview:
| Certification Vendor: | CIMA |
|---|---|
| Exam Name: | Fundamentals of Management Accounting (P1 / BA2 legacy reference) |
| Exam Number: | BA2 |
| Related Certifications: | CIMA Certificate in Business Accounting (BA1-BA4) CIMA Professional Qualification (Operational level) |
| Exam Duration: | 120 minutes |
| Real Exam Qty: | 60 |
| Certificate Validity Period: | No expiry (Certificate qualification does not expire once awarded) |
| Passing Score: | 50% |
| Exam Format: | Objective Test, Multiple Choice Questions |
| Available Languages: | English |
| Recommended Training: | CIMA Official Certificate in Business Accounting |
| Exam Registration: | CIMA Exam Registration |
| Sample Questions: | ![]() |
| Exam Way: | Computer-based exam delivered at test centers or online proctored (where available). |
| Pre Condition: | No formal prerequisites required for Certificate level entry. |
| Official Syllabus URL: | https://www.aicpa-cima.com/cimaexams/certificate-in-business-accounting |
CIMA CIMAPRO19-P01-1 Exam Syllabus Topics:
| Section | Objectives |
|---|---|
| Standard Costing and Variance Analysis | - Interpretation of variances - Material, labor, and overhead variances |
| Short-term Decision Making | - Make or buy and limiting factors - Relevant costing principles |
| Budgeting | - Cash and functional budgets - Budget preparation and purpose |
| Cost-Volume-Profit Analysis | - Break-even analysis - Contribution and margin of safety |
| Costing Techniques | - Overhead allocation and absorption - Absorption and marginal costing |
| Introduction to Management Accounting | - Cost classification and cost behavior - Role and purpose of management accounting |
Everything About the CIMA Management Accounting — FAQ
Head to the vendor's official registration channels:
One detail worth checking at booking: the CIMAPRO19-P01-1 exam runs Computer-based exam delivered at test centers or online proctored (where available)., so choose the format you are most comfortable with.
The vendor officially recommends:
Take the courses for the theory, then switch to measurement: the CIMAPRO19-P01-1 practice questions from CertkingdomPDF — with auto-graded mock tests — show you what is actually sticking.
You're looking at 60 questions in 120 minutes. Do the math early, not in the exam room: decide your per-question pace, practice skipping hard items without panic, and finish at least two full timed mock tests — the CertkingdomPDF engine grades them automatically in about a minute, so you get instant feedback on where your time goes.
Delivery is the easy part: pay, click the email link that arrives within a minute, and the CIMAPRO19-P01-1 files download in about a minute — no extra software, no installation limits. If 2 hours pass with nothing, our support team will fix it. The refund side runs on clear rules: take the corresponding CIMAPRO19-P01-1 exam within 60 days of purchase, and if you fail, submit a scanned enrollment slip plus the official Score Report PDF within 2 days of the exam for a 100% refund, processed within 7 days. Exams sat within 3 days of purchase don't qualify, candidate and payer names must match, and free or expired products are excluded. Prefer an exchange? Take two equal-value exam products free of charge and keep your original updates.
The vendor's blueprint for the CIMA Management Accounting has 6 domains, led by Introduction to Management Accounting, Short-term Decision Making, Cost-Volume-Profit Analysis. The weighting is a study plan in disguise — heavy domains deserve heavy hours. You'll find every domain and subtopic in the complete outline above.
Passing the CIMAPRO19-P01-1 exam earns the CIMA Certificate in Business Accounting (Cert BA) certification — a Certificate-level credential — issued directly by CIMA. It is proof of ability that travels well across employers and borders. The credential also links to CIMA Certificate in Business Accounting (BA1-BA4), CIMA Professional Qualification (Operational level), so it can be a first step rather than a final destination.
Yes — the free PDF demo shows the real question quality before any payment. And the value continues after purchase: 365 days of free updates come standard, with a 50% renewal discount if your update period ever expires.
No formal prerequisites required for Certificate level entry. These rules do get revised, so before you book, double-check the current requirements on the official CIMAPRO19-P01-1 exam page — what the vendor publishes is what counts.
CIMA Management Accounting Sample Questions:
A company is launching a new product with a selling price of $20.
Demand and variable cost are both uncertain and possible demand levels and variable costs are given below:
Outcomes for demand and variable cost are independent.
What is the expected contribution from the product?
Give your answer as a whole number.
Correct Answer:
$6384
A completed unit of Product A requires 9 kg of material and 10% of material is wasted in the production process.
Material has a standard cost of $5 per kg.
Product A also requires 4 labour hours at a standard cost of $10 per labour hour and variable overheads at a standard cost of $2 per labour hour What is the standard variable production cost per unit of Product A?
- A. $93
- B. $50
- C. $97.50
- D. $98
Correct Answer: D 🗳️
XY manufactures a range of products and uses an activity based costing system.
Budgeted production of Product B is 7,500 units.
Overheads have been identified by activity and related to appropriate cost drivers.
Product B is produced in batches of 250 units. Machines have to be reset after every batch and quality inspections are carried out on every third batch.
What is the total overhead cost per unit of Product B?
Give your answer to two decimal places.
Correct Answer:
$1.40
MBM is considering introducing a new product and has to decide if the sales price should be $80, $90,
$100 or $120.
There is a 30% chance that demand could be high, a 50% chance that demand will be at a medium level and a 20% chance that demand will be low.
A payoff table below shows the profits based on the sales price and the level of demand.
MBM has decided, using an expected value approach, that the sales price should be set at $80 as this gives the highest expected profit of $860,000.
A market research company has since approached MBM offering to provide perfect information on the demand level.
What is the maximum amount that should be paid for the perfect information?
Give your answer as a whole number (in '000s).
Correct Answer:
$60000
The standard production cost of making a product is as follows:
What is the fixed production overhead capacity variance?
- A. $6,000F
- B. $3,000F
- C. $9,000F
- D. $6,000A
Correct Answer: A 🗳️